Body Shop Project Update

Wednesday, November 16, 2016 · Jarrett- Gordon Ford Davenport Body Shop

img_2475img_2495img_0552img_0549

 

 

 

 

 

 

 

 

 

 

 

 

 

Roofing, wall sheeting, interior framing and overhead doors are complete at Jarrett-Gordon Ford of Davenport. Electricians are beginning electrical rough in, and fire suppression will be completed by the end of this week. Tucker crews have prepped and formed footers for 270 foot long retaining wall.